DIRECT ANSWER

DOB names Alfonso’s Home Improvement on the general construction, structural, foundation and fence permits at BIN 5019938. The GC, structural and foundation filings show LOC Issued with an April 14, 2026 sign-off date; plumbing S01317123-S5 remains Permit Entire, and a separate whole-house wiring application remains Job in Process. Use this dossier to distinguish those scopes, identify the evidence still missing and build a bid that keeps each trade and closeout obligation visible.

Publication type
Project dossier
Topic
Project dossiers
Sources
8 primary references
Verified as of
November 11, 2026

One renovation, several different evidence states

The address is 623 Ingram Avenue, Staten Island, NY 10314, BIN 5019938, BBL 5007770067. This dossier follows the renovation job S01317123 and checks other work recorded at the same BIN. Research was checked on November 11, 2026. It is an investigation of public records, with practical comparisons derived from those records; we have not inspected the house or interviewed the owner, architect or contractors.

The DOB filing for general construction describes a two-story building with a cellar. It records one existing and one proposed dwelling unit. PLUTO 26v2 instead records building class B2, two residential units, two floors and a 1970 year-built value. These are different administrative sources, not a basis for deciding the house’s legal occupancy. Before using this project as a reference for a conversion, obtain the occupancy record and approved plans. A Letter of Completion does not resolve that discrepancy by itself. See DOB’s CO and Letter of Completion guidance.

THE USEFUL DISTINCTION

The general construction, structural and foundation filings record LOC Issued. Plumbing remains Permit Entire, while the same-address whole-house wiring application remains Job in Process. “The renovation is signed off” would hide those separate statuses.

Who holds each construction permit

The permit dataset names ALFONSO’S HOME IMPROVEMEN, GC 608017, on four construction work types. The job-filings dataset names Focal Point Architects & Ass., RA 040256, as the design applicant. Those are different roles even though both datasets use an “applicant” field. The names and numbers below describe the reviewed filings; they do not replace a current license and insurance check before hiring.

S01317123 construction filings and permits, checked November 11, 2026. Short suffixes belong to this job.
Filing / work permitNamed permit holderIssue dateFiling status / permit status
I1 / S01317123-I1-FNAlfonso’s, GC 608017 · construction fenceDecember 19, 2025LOC Issued / Signed-off · sign-off March 26, 2026
S1 / S01317123-S1-GCAlfonso’s, GC 608017 · general constructionDecember 22, 2025LOC Issued / Signed-off · sign-off April 14, 2026
S3 / S01317123-S3-STAlfonso’s, GC 608017 · structuralDecember 22, 2025LOC Issued / Signed-off · sign-off April 14, 2026
S4 / S01317123-S4-FOAlfonso’s, GC 608017 · foundationDecember 22, 2025LOC Issued / Signed-off · sign-off April 14, 2026
S5 / S01317123-S5-PLP.S.I. Mechanical · license 001790, type PDecember 23, 2025Permit Entire / Permit Issued · no sign-off date returned

The plumbing row is particularly useful: it identifies a trade permit holder rather than requiring an inference from the GC’s project history. Its recorded expiry is December 23, 2026. An expiry in the future is not a completion approval. The four Alfonso’s permits record an October 17, 2026 expiry alongside Signed-off; expiry and closeout are separate fields.

Sources: I-P permits and I-F filings.

What “gut renovation” includes at this address

The general construction description spans the cellar, first floor and second floor, plus the facade and rear construction. It is broader than a kitchen-and-bath refresh. The related structural and foundation descriptions add information absent from the GC summary.

Recorded work versus the information needed to price or evaluate it.
Work packageWhat DOB recordsWhat the record leaves unspecified
Interior across three levels · S1Interior gut renovation; new walls and framing at cellar, first and second floors.Room layouts, retained finishes, partition lengths, assemblies and a demolition or finish schedule.
Rear second-floor construction · S1Removal of the rear extension on the second floor.Measured removal limits, retained structure, temporary protection and reinstatement details.
Facades and rear deck · S1Replacement facades; proposed new deck on the existing rear foundation wall.Facade material, replacement area, deck size, connections and confirmation of the retained wall’s suitability.
Structure and openings · S3Structural changes to “exp 1 & 4,” removal and rebuilding of a door entry, an addition and reframing of larger windows.The meaning and locations of “exp 1 & 4,” member sizes, bearing, connections and opening dimensions. The abbreviation is preserved, not guessed.
Footings · S4Footing changes associated with the entry, addition and larger-window work.Footing geometry, soil/bearing assumptions, excavation limits and inspection results.
Plumbing · S5A plumbing application filed in conjunction with the main application; floors 001–002.Fixture counts, branch/stack replacement, pipe material, gas scope and whether cellar plumbing is included.
Site separation · I1An eight-foot plywood construction fence.Its plan, extent, duration and the final removal arrangements.

The GC summary’s removal of a rear extension and the structural summary’s reference to an addition should be read together against the drawings. The text alone cannot establish whether they refer to the same location, a redesigned proposal or different parts of the building. A bidder should mark both on one drawing set before pricing.

For another house, the transferable lesson is the division into packages. The cellar, occupied floors, exterior envelope and rear structure create different quantities and interfaces. A single “complete gut” allowance gives no way to check whether two proposals cover the same work.

The filing history is not a construction diary

DOB’s Build FAQ defines I as initial, S as subsequent and P as a post-approval amendment. The ten returned rows in the S01317123 family therefore do not mean ten completed projects.

Administrative chronology from filing and permit dates.
DateRecorded eventHow to use it
November 11–14, 2025I1 and S1 filed November 11; S3/S4 November 12; S5 November 13. Their approval dates fall November 12–14.Establishes the related work types before the later permit issuances; it does not establish the first day on site.
December 1–8, 2025P1/P2 repeat the GC description; P3 repeats the structural description; P4 repeats the foundation description. All record Approved.The summaries do not expose the drawing revisions. Compare approved revisions rather than treating unchanged text as unchanged design.
December 19–23, 2025Fence permit issued December 19; GC, structural and foundation December 22; plumbing December 23.Five separate work-permit identifiers, with different responsibilities.
March 25–26, 2026P6 plumbing amendment filed March 25 and approved March 26. Fence I1 sign-off date March 26.Fence closeout does not close the plumbing application. The plumbing summary still gives no fixture schedule.
April 14, 2026S1, S3 and S4 record sign-off dates and LOC Issued.Evidence of administrative closeout for those filings. No issued LOC document or inspection report was downloaded for this dossier.

The interval from permit issuance to a sign-off entry is not a measured construction duration. Procurement, inactive periods, inspection scheduling and record updates are not reconstructed here. No start-to-finish performance claim is made about Alfonso’s.

Electrical work has its own companies and statuses

The electrical dataset returns three same-BIN applications. None returns a construction-job reference in the selected const_bis_job_number field. Their address and timing make them useful context; they do not prove a subcontract to Alfonso’s or that every electrical item formed part of the same renovation contract.

Same-address electrical applications; scope paraphrased from the records.
Electrical filingNamed firm / licenseRecorded scopeReviewed status
S01278699-I1-EL · issued August 27, 2025Amber Electl Contng Inc · Electrician 01259834-panel roof PV system, feeders, service switch and 125A combo panel.Complete / Job is complete
S01316100-I1-EL · issued November 9, 2025First Quality Elecl LLC · Electrician 013370General wiring of the entire house.Permit Issued / Job in Process
S01344867-I1-EL · issued January 11, 2026Amber Electl Contng Inc · Electrician 012598Two 125A combo service panels and two sets of #3 feeders.Complete / Job is complete

We use the explicit status fields, not the electrical dataset’s completion_date alone: the open whole-house wiring row contains a future date. A dated field must not override “Job in Process.” Separate construction solar filing S01283415-I1 also appears at this BIN, naming Sunday Energy LLC on the permit; it is not part of job S01317123 and is excluded from the renovation cost discussion.

For an owner comparing gut-renovation proposals, this is a concrete reason to ask who covers branch wiring, service equipment and solar interfaces, and which closeout belongs to each. DOB’s residential alteration guidance describes the separate electrical permit and licensed electrical contractor role. A GC reference does not establish that role.

The $338,300 figure is a filing estimate

S1 records an initial/estimated job cost of $338,300. P1 and P2 repeat that value. The reviewed structural, foundation, fence and plumbing rows each record $1,000. These are filing figures; no signed contract, schedule of values, paid invoice, change-order ledger or final cost affidavit was reviewed.

Do not add the amendment rows to calculate a project total. Do not treat the repeated $1,000 entries as credible installed prices for complete structural, foundation or plumbing packages. The dataset does not explain how cost was allocated among these filings.

The GC filing also records 3,383 square feet of total construction floor area, whereas PLUTO records 2,086 square feet of building area. We have no measured plans reconciling those fields. Dividing $338,300 by either figure would create a precise-looking renovation rate with an unverified denominator and unverified cost coverage. This dossier therefore does not publish a $/sq-ft benchmark.

For a useful estimate, first measure the work by level and component. Require a separate cost for demolition, partitions/framing, exterior work, rear structure, plumbing, electrical, finishes, professional/filing fees and access. Identify allowances, owner-supplied items and concealed-condition pricing before comparing totals.

Listed requirements versus completed inspection evidence

The application data lists these requirements. It does not include the individual reports, test results or photographs. Even where LOC Issued is returned, the list itself is not a record of a particular inspector’s visit.

Inspection requirements recorded on the principal construction filings.
FilingSpecial inspection fieldProgress inspection field
S1 · general constructionFire-resistant penetrations and joints.Energy code compliance; final; fire-resistance-rated construction.
S3 · structuralMasonry; structural cold-formed steel; structural steel details; prefabricated wood I-joists.Final.
S4 · foundationNo value returned in this field.Final; footing and foundation.

The steel and I-joist labels do not establish the installed member schedule, quantity or location. The absence of a value in S4’s special-inspection field is not a blanket exemption. Obtain the actual technical reports and approved documents for the work being evaluated. DOB’s sign-off guidance explains why inspection reports and final submissions matter in closeout.

Use the record to make your own bids comparable

This is an owner’s comparison worksheet derived from the interfaces above, not the recorded contract or construction sequence at 623 Ingram. Give each bidder the same approved drawing revision. For every line record a quantity, fixed price or allowance, responsible firm, exclusions and the document that will demonstrate completion.

Copy these packages into the same scope sheet for each bidder.
PackageMake the bid measurableEvidence to agree before award
Cellar / first floor / second floorList each level’s demolition, retained items, wall/ceiling assemblies and finish allowances separately.Marked plans and schedules; room-by-room exclusions; inspection and punch-list responsibility.
Entry, addition and larger openingsIdentify each opening and structural intervention; separate temporary work from permanent construction.Coordinated architectural/structural revisions, design responsibility, approved changes and concealed-work records.
Rear extension removal / deck / footingsShow removal limits, retained wall, new footprint, excavation and restoration limits.Designer’s details and inspections; written price rule for unexpected existing conditions before they arise.
Facade replacementState elevations, area, material, opening interfaces and what remains.Specification, sample approval, interface details and photographs before concealment.
PlumbingList fixtures and piping work by floor; state whether cellar, gas and service work are included.Named trade contractor, applicable filing, test/inspection obligations and separate closeout status.
Wiring / service equipment / PV interfacesSeparate branch wiring, devices, lighting, panels and solar work; identify owner-supplied equipment.Named electrical firm, permit scope, utility coordination where applicable and electrical closeout.
Protection, fees and closeoutIdentify fence, debris, temporary weather protection, fees, allowances and removal costs.Milestone schedule, change-order procedure, filing-by-filing closeout list, warranties and final punch list.

Three answers make a reference check much more useful: which of these packages the company actually performed, which it subcontracted, and which documents the owner can provide to confirm the result. A reference for interior finishes alone does not establish experience with an addition, footing changes or coordinated trade closeout.

What would turn this into a verified built-work case study

The public records support a substantial renovation scope and named permit holders. They do not yet support an illustrated “before → process → finished result” account. The next material request should be specific:

  1. Approved plans and amendment index: S1/S3/S4/S5 plus P1–P4 and P6, with the revisions mapped to their parent filings. This would resolve the extension/addition relationship and quantify the work.
  2. Closeout documents: issued LOCs, inspection/technical reports, and the current plumbing and whole-house electrical status. This would separate closed construction packages from unresolved trade records.
  3. Dated photographs with reuse permission: pre-demolition views, opened structural/foundation conditions, facade/deck interfaces before concealment and matched finished views. Each image should identify the location and responsible company.
  4. A redacted scope and cost record: signed scope, schedule of values, allowances and changes. This would establish cost coverage rather than treating the filing estimate as a paid price.
  5. Project-team confirmation: who performed each package, the relationship between the same-address electrical jobs and the renovation, and a permissioned owner reference. This would establish execution roles that an address match cannot.

The DOB NOW public portal displayed a US-only access restriction during this research, so its drawings and issued documents were not reviewed. This is an access limitation, not a finding that the documents do not exist. No project photographs, performance measurements, owner testimonial or workmanship rating are implied by this dossier.

Check the exact official records

The narrative and tables remain readable without loading external data. Expand a source to load a short preview from NYC Open Data; use its Original JSON link for all returned rows. Queries are bounded to the identifiers above. A current response can differ from this dated review.

Show dataHide dataI-F · S01317123 filings, amendments and sign-off dates
Show dataHide dataI-P · S01317123 named permit holders and permit statuses
Show dataHide dataI-E · All three same-BIN electrical applications
Show dataHide dataI-L · PLUTO 26v2 tax-lot characteristics
Show dataHide dataI-O · Filing occupancy and construction-area fields
Show dataHide dataI-T · Listed inspection requirements for S1, S3 and S4

Continue with the building record, Alfonso’s contractor record, or Staten Island gut-renovation comparison. These links serve different checks: the dossier explains the project; the contractor record holds the dated company checks.

PRIMARY REFERENCES

Sources

These links are provided so you can check the current official guidance and public systems yourself. Rules and portal records can change.

  1. Filing identity, design applicant, scope, amendments, inspection requirements and filing status. Exact filtered queries appear in the dossier.

  2. NYC Department of BuildingsDOB NOW: Build — Approved Permits ↗

    Named permit holder, trade, issuance/renewal sequence and permit status. A row is not necessarily a separate project.

  3. Electrical firms and application/job statuses. Same-address records are separated from a documented link to the construction job.

  4. Tax-lot context. Multi-building lot totals must not be represented as a single building’s quantities or as a legal occupancy determination.

  5. General construction, design-professional and separate plumbing/electrical roles for owner planning.

  6. NYC Department of BuildingsProject sign-off and completion ↗

    Completion reports and inspection closeout are different evidence from an issued permit or a listed inspection requirement.

  7. A CO establishes legal use/occupancy; a Letter of Completion is not a substitute for reviewing the building’s occupancy record.

  8. I, S and P suffixes identify initial, subsequent and post-approval-amendment filings. Search public records by BIN.