DIRECT ANSWER
Permit Issued records authorization for a particular work permit; it does not establish completion. In DOB NOW, Signed-off is a permit closeout status, while LOC Issued refers to the job’s Letter of Completion. BIS also uses Signed Off at the job-filing level. A past expiration date calls for a current renewal and status check. Compare the exact address or BIN, job number, work type, named contractor and dates. These records document an administrative stage, not a workmanship rating.
- Guide type
- Focused guide
- Topic
- Read permits and public records
- Sources
- 8 primary references
- Verified as of
- October 6, 2026
What does the NYC DOB permit status mean?
Read the status at both levels: an individual work permit and the job filing containing it. The same building can have several jobs, and one filing can have several work types. DOB NOW and BIS do not use every label at the same level: BIS also uses Signed Off for a completed job filing.
| Status or date | What it records | What to check next |
|---|---|---|
| Approved | The application has reached approval and a work permit can be created. | Find the issued permit for the relevant work type; approval alone is not permit issuance. |
| Permit Issued / Permit Entire | A work permit has been issued. Permit Entire is the filing stage where permits for each work type have been issued. | Compare scope, named contractor, issuance, expiration and any later amendment or renewal. |
| Signed-off | In DOB NOW, a permit has reached its recorded closeout stage. | Check the work type, final inspection or required closeout notification, and whether the other permits on the job are closed. |
| LOC Issued | A Letter of Completion has been issued for the job filing. | Open the letter and compare its job and scope. Certificate of Occupancy filings follow a different completion path. |
| Expiration date in the past | The dated permit record shows an elapsed term. | Check the live permit, renewals and current status before treating it as authorization for work today. |
The DOB filing-status reference explains filing stages and BIS equivalents. The DOB NOW Build FAQs distinguish permit sign-off from job-level completion. Temporary construction equipment can use a removal notification for closeout; a Signed-off label does not describe one universal inspection process.
How to find the exact DOB permit record
Start with the official DOB NOW and BIS search instructions. Search both systems for filing history, using the BIN when available. Match the address, job number, permit work type, legal business name or license identifier, and the date of the result.
For a DOB NOW Letter of Completion, open the property’s BUILD job filings, select the job, and view the completion document. DOB’s Letter of Completion guidance explains public access and the separate BIS process.
A DATED PERMIT EXAMPLE
Our September 27, 2026 catalog check recorded permit M01045312-I1-GC at 614 West 152nd Street as Signed-off. The scope names B&H Restoration for opening brickwork, installing waterproofing above windows, and reinstating the brick.
That status belongs to this permit and scope. It does not establish that every leak at the building was resolved. Use the dated scope summary and exact official query, then check the current DOB record.
What a permit can show
An issued DOB permit can be strong evidence that New York City authorized a named permit holder to perform defined work at a particular property under a particular job filing. Depending on the record, it may show:
- job and permit numbers;
- BIN, BBL, borough, and address;
- work type and a description of the proposed scope;
- applicant, contractor, permittee, or license number;
- issuance and expiration dates;
- permit or job status.
Those fields are useful only when read as a dated record. A later amendment, renewal, withdrawal, or correction may change the project history.
Do not merge filing, permit, and sign-off
A job filing is the application record for proposed work. A permit is the authorization to proceed under that filing and its conditions. A sign-off, letter of completion, or related closeout record addresses a later stage.
Therefore:
- a filed scope is not automatically an issued permit;
- an issued permit is not proof that every described item was completed;
- completed physical work is not automatically signed off;
- an expired permit does not erase the historical fact that it was issued.
The official status and the date of the search belong in any summary.
Read named participants by role
The applicant of record, design professional, contractor, permittee, owner, and subcontractor are not interchangeable roles. A company named on one permit may not be the prime contractor for the whole renovation. Conversely, a masonry subcontractor may not appear in the public row you are reading.
When using a permit to support a contractor-project connection, match the contractor or permittee identifier, legal name, address, and company-published project information. Do not assign responsibility for every item in a broad filing to one participant without evidence.
EVIDENCE STANDARD
A permit match supports the named relationship and scope in the record. It is not a rating and does not establish responsibility beyond that evidence.
What a permit does not prove
By itself, a permit does not prove:
- workmanship quality or durability;
- that the project stayed within budget or schedule;
- that every proposed item was completed;
- that every worker or subcontractor is named;
- that the named company holds every license required today;
- that no other work occurred at the building;
- that the owner, architect, contractor, and DOB agree about a later dispute.
It is also unsafe to infer that no work occurred because no matching permit was found. Some repair work does not require a DOB permit, old records can sit in another system, address searches can miss a building, and work may appear under another party.
Use permits to improve due diligence
For a contractor claim, use the permit to ask concrete questions:
- Does the company identify the same address and work?
- Does the BIN resolve to the claimed building?
- Which participant and license number appear?
- Was the permit issued during the claimed project period?
- Does the scope resemble the experience being presented?
- Is there a later status, amendment, inspection, or closeout record?
Then check the contractor’s current DCWP and entity information separately. Current licensing and historical permit participation are related evidence, not substitutes for one another.
PRIMARY REFERENCES
Sources
These links are provided so you can check the current official guidance and public systems yourself. Rules and portal records can change.
- NYC Department of BuildingsFind Building Data ↗
Official overview of BIS, DOB NOW Public Portal, permits, complaints, violations, and building history.
- NYC Department of BuildingsDOB NOW ↗
Official description of DOB NOW Build, Safety, Inspections, and Licensing functions.
- NYC Department of BuildingsFiling Statuses for DOB NOW: Build & BIS Jobs ↗
Official status reference distinguishing plan approval, permit issuance, Permit Entire, LOC Issued, and the corresponding BIS filing stages.
- NYC Department of BuildingsLetter of No Objection or Completion ↗
Official explanation of Letter of Completion requirements, permit sign-off, public access to the issued document, and separate BIS closeout requests.
- NYC Department of BuildingsDOB NOW: Build frequently asked questions ↗
Official guidance stating that DOB NOW filings do not appear in BIS, that both systems should be searched, and that BIN search is more inclusive than address search.
- NYC Department of BuildingsContractors ↗
Official explanation that registration requirements depend on the work and that DCWP issues Home Improvement Contractor licenses.
- NYC Department of Consumer and Worker ProtectionQuick tips when hiring a home improvement contractor ↗
Official consumer guidance on license checks, written estimates, permit disclosure, and the Home Improvement Contractor Trust Fund.
- NYC Landmarks Preservation CommissionPermit types ↗
Official explanation of work requiring LPC review and the separate roles of LPC and DOB approvals.